| After you have established baseline data in your plan, you will need to be able to use it to analyze your progress. Viewing Baselines In the Tracking Gantt - Save your baseline using the steps described in the previous tasks .
- Click the View, Tracking Gantt menu item.
- Notice the dark bars below the "normal" Gantt bars. These dark bars represent the baseline start\finish dates.
Using the Multiple Gantt Chart View - Click the View, More Views menu item.
- Select Multiple Baseline Gantt from the list.
- The baseline values are shown in blue.
- Baseline1 values are colored in maroon.
- Baseline2 values are colored in green.
- Using this view, you can see the date-slipping trends across the times that baselines were saved.
Applying the Baseline Table to View Baseline Data - Click the View, Table, More Tables menu item.
- Select Baseline.
- Click Apply.
- View your baseline data.
Did You Know? Instead of having to insert baseline fields into your views, you can use the tracking table . The tracking table, which already comes with Project, already contains the Duration, Start, Finish, Work, and Cost fields for that baseline. | |