The Resource Sheet view is the view most commonly used to view and edit information about resources. Here is the place to define how much a resource costs per hour , what their maximum allocation level is, and other detailed data. Viewing a Resource Sheet - Resource Name displays the name of the resource.
- Max Units defines the percentage of a full working day that a resource is available for work.
- Standard Rate and Overtime Rate define the cost of using a resource.
Did You Know? It's not a good idea to have two resources with the same name . Although it is possible to have two resources with the same name, it is not a good idea, as it can become very confusing when trying to analyze resource allocations later in the project. | For Your Information Resource Naming Restrictions A resource name may not contain the square bracket characters ([]) or the system list separator character. This is a comma by default, but in some countries it's a period. Project 2003 will not allow you to have these characters in your resource names . | |