Show Me Microsoft Office Project 2003

     

The Resource Sheet view is the view most commonly used to view and edit information about resources. Here is the place to define how much a resource costs per hour , what their maximum allocation level is, and other detailed data.

Viewing a Resource Sheet

Resource Name displays the name of the resource.

Max Units defines the percentage of a full working day that a resource is available for work.

Standard Rate and Overtime Rate define the cost of using a resource.

Did You Know?

It's not a good idea to have two resources with the same name . Although it is possible to have two resources with the same name, it is not a good idea, as it can become very confusing when trying to analyze resource allocations later in the project.

For Your Information

Resource Naming Restrictions

A resource name may not contain the square bracket characters ([]) or the system list separator character. This is a comma by default, but in some countries it's a period. Project 2003 will not allow you to have these characters in your resource names .