The General tab of the Resource Information dialog Project allows you to contour the Max Units for a resource over time. This means that you can specify a date range and the Max Units for that resource during that time period. This can be useful when you know that a specific resource will only be available to your project half-time for the month of June, but then full- time for July and August, and then half-time again in September. Defining Constant Availability - Double-click on the resource you want to define.
- To set the resource so that it has a constant Max Units over time, make sure that the Available From and Available To fields both read NA.
- Make sure that the Units value equals the Max Units value you want to set for the resource.
- Click OK to save your changes.
|