This appendix contains a list of metrics that your organization can consider using. For more information, review Chapter 17.
Level 2
Requirements Management
-
Requirements volatility (percentage of requirements changes)
-
Number of requirements by type or status (defined, reviewed, approved, and implemented)
-
Cumulative number of changes to the allocated requirements, including total number of changes proposed, open , approved, and incorporated into the system baseline
-
Number of changes requests per month, compared to the original number of requirements for the project
-
Number of time spent, effort spent, cost of implementing change requests
-
Number and size of change requests after the Requirements phase is finished
-
Cost of implementing a change request
-
Number of change requests versus the total number of change requests during the life of the project
-
Number of change requests accepted but not implemented
-
Number of requirements (changes and additions to the baseline)
Project Planning
-
Completion of milestones for the project planning activities compared to the plan (estimates versus actuals)
-
Work completed, effort expended, and funds expended in the project planning activities compared to the plan
-
Number of revisions to the project plans
-
Cost, schedule, and effort variance per plan revision
-
Re-planning effort due to change requests
-
Effort expended over time to manage the project compared to the plan
-
Frequency, causes, and magnitude of the re-planning effort
Project Monitoring and Control
-
Effort and other resources expended in performing monitoring and oversight activities
-
Change activity for the project plan, which includes changes to size estimates of the work products, cost estimates, resource estimates, and schedule
-
Number of open and closed corrective actions or action items
-
Project milestone dates (planned versus actual)
-
Number of project milestone dates made on time
-
Number and types of reviews performed
-
Schedule, budget, and size variance between planned versus actual reviews
-
Comparison of actuals versus estimates for all planning and tracking items
Measurement and Analysis
-
Number of projects using progress and performance measures
-
Number of measurement objectives addressed
Supplier Agreement Management
-
Cost of the COTS (commercial off-the-shelf) products
-
Cost and effort to incorporate the COTS products into the project
-
Number of changes made to the supplier requirements
-
Cost and schedule variance per supplier agreement
-
Costs of the activities for managing the contract compared to the plan
-
Actual delivery dates for contracted products compared to the plan
-
Actual dates of prime contractor deliveries to the subcontractor compared to the plan
-
Number of on-time deliveries from the vendor, compared with the contract
-
Number and severity of errors found after delivery
-
Number of exceptions to the contract to ensure schedule adherence
-
Number of quality audits compared to the plan
-
Number of senior management reviews to ensure adherence to budget and schedule versus the plan
-
Number of contract violations by supplier or vendor
Process and Product Quality Assurance (QA)
-
Completions of milestones for the QA activities compared to the plan
-
Work completed, effort expended in the QA activities compared to the plan
-
Numbers of product audits and activity reviews compared to the plan
-
Number of process audits and activities versus those planned
-
Number of defects per release or build
-
Amount of time/effort spent in rework
-
Amount of QA time/effort spent in each phase of the life cycle
-
Number of reviews and audits versus number of defects found
-
Total number of defects found in internal reviews and testing versus those found by the customer or end user after delivery
-
Number of defects found in each phase of the life cycle
-
Number of defects injected during each phase of the life cycle
-
Number of noncompliances written versus number resolved
-
Number of noncompliances elevated to senior management
-
Complexity of module or component (McCabe, McClure, and Halstead metrics)
Configuration Management (CM)
-
Number of change requests or change board requests processed per unit of time
-
Completions of milestones for the CM activities compared to the plan
-
Work completed, effort expended, and funds expended in the CM activities
-
Number of changes to configuration items
-
Number of configuration audits conducted
-
Number of fixes returned as "Not Yet Fixed"
-
Number of fixes returned as "Could Not Reproduce Error"
-
Number of violations of CM procedures ( noncompliance found in audits)
-
Number of outstanding problem reports versus rate of repair
-
Number of times changes are overwritten by someone else (or number of times people have the wrong initial version or baseline)
-
Number of engineering change proposals proposed, approved, rejected, implemented
-
Number of changes by category to code source, and to supporting documentation
-
Number of changes by category, type, and severity
-
Source lines of code stored in libraries placed under configuration control