16.1 Flow of an Individual Estimate on a Poorly Estimated Project
On poorly estimated projects, the creation of the estimate flows as shown in Figure 16-1.
The inputs, the estimation process, and the outputs are not well defined, and they are open to debate and scrutiny. Scrutinizing the estimation process would be beneficial if the objective were to obtain more accurate results. But the objective of the scrutiny is usually to make the estimate smaller. In other words, the scrutiny tends to put downward pressure on the estimate, which is not offset by any corresponding upward pressure.
| Tip #69 | Don't debate the output of an estimate. Take the output as a given. Change the output only by changing the inputs and recomputing. |