Passing the PMP Exam: How to Take It and Pass It: How to Take It and Pass It

1.

The ________ is the document that starts the entire Project Time Management process.

A.

Charter

B.

SOW

C.

RFP

D.

Scope Statement

2.

Decomposition of the Scope Statement results in the ________.

A.

Project plan

B.

WBS

C.

SOW

D.

Schedule

3.

You break down the WBS into smaller ________ to get detail so that you can construct a schedule.

A.

Work packages

B.

Time components

C.

Sections

D.

Issues

4.

When using decomposition in activity definition, the final output is:

A.

Deliverables

B.

Work packages

C.

Activities or action steps

D.

Schedule

5.

Updates to the WBS during activity definition are often called:

A.

Supporting detail

B.

Refinements

C.

Updates

D.

Activities

6.

A form of progressive planning is called:

A.

Scheduling

B.

Charting

C.

Expanded trial

D.

Rolling wave

7.

The major output from activity definition is:

A.

The schedule

B.

The activity list

C.

WBS

D.

SOW

8.

Other outputs from activity definition are:

A.

Activity attributes, Milestone lists

B.

WBS, SOW

C.

Technical requirements, and the WBS

D.

Activity costs, schedule costs

9.

Milestones are:

A.

Activities with durations

B.

Significant events in the project life cycle

C.

Cost measurements

D.

Denote start and finish of all activities

10.

Three types of dependencies are mandatory, discretionary, and ________.

A.

Easy

B.

Planned

C.

Internal

D.

External

11.

How long is the duration for a milestone?

A.

0 days

B.

3 days

C.

It depends

D.

5 days

12.

The type of dependency that is used by Microsoft Project is a ________ dependency.

A.

Start-to-finish

B.

End-to-end

C.

Finish-to-start

D.

Start-to-end

13.

Starting a new computer system before turning the old one off is an example of a(n) ________ dependency.

A.

Start-to-finish

B.

End-to-end

C.

Finish-to-start

D.

Natural

14.

Which Network Diagramming Method uses dummy activities?

A.

PDM

B.

GERT

C.

PERT

D.

ADM

15.

PDM is also known as what?

A.

Activities on nodes

B.

Activities dependencies

C.

Activities on arrows

D.

Activities sequencing

16.

PDM stands for:

A.

Positive Daily Mechanisms

B.

Process Diagramming Method

C.

Precedence Daily Management

D.

Precedence Diagramming Method

17.

Conditional branches can be found in:

A.

GERT

B.

PERT

C.

PDM

D.

AON

18.

A schematic display of the project's activities and the logical relationships among them is a(n) ________.

A.

Technically difficult process

B.

Working Schedule

C.

Project network diagram

D.

Schedule diagram

19.

________ are a high-level compilation of the tasks below them.

A.

WBS

B.

Summary tasks

C.

Schedules

D.

PDM

20.

The project plan is developed by:

A.

The manager of project managers

B.

Executive management

C.

The project team and manager

D.

Sponsors

21.

The project schedule is developed in the ________ phase.

A.

Execution

B.

Initiation

C.

Planning

D.

Conceptual

22.

Estimating databases and other historical data are examples of ________ that might be helpful in estimating durations.

A.

Records

B.

Organizational assets

C.

Written data

D.

Electronic information

23.

Top-down estimating is also known as ________ estimating.

A.

Organizational

B.

Simple

C.

Analogous

D.

Primary

24.

Which technique below is the most common simulation technique?

A.

GERT

B.

Monte Carlo

C.

Linear Analysis

D.

Decompression

25.

Rules of thumb are known as ________.

A.

Leveling Heuristics

B.

Common sense

C.

Problem solvers

D.

Monte Carlo analysis

26.

Monte Carlo simulation is done using ________ scenarios.

A.

Simple

B.

Technical

C.

Common

D.

Multiple

27.

What tasks would you Fast Track to shorten the project duration in the Critical Path in Figure 10-9?

A.

E & G

B.

B, D, & E

C.

C & F

D.

C & G

28.

Doing more activities in parallel is called ________.

A.

Fast Tracking

B.

Schedule clearing

C.

Compressed work

D.

Planning compression

29.

Bar charts do not show ________.

A.

Time constraints

B.

Dependencies

C.

Partial tasks

D.

All of the above

30.

The approved project schedule is called the:

A.

Sponsored schedule

B.

Performance schedule

C.

Baseline schedule

D.

Approved schedule

31.

Anything done to bring expected future schedule performance in line with the project plan is known as ________.

A.

Replanning

B.

Schedule arrangement

C.

Corrective actions

D.

Rebaselining

32.

If you update the schedule, the updates must be approved by the ________.

A.

Project manager

B.

Project Team

C.

Line management

D.

Sponsor

33.

Revisions are a special type of schedule updates that make changes to:

A.

Costs

B.

Resources

C.

Same as Fast Tracking

D.

Start/Finish Dates

34.

Rebaselining should occur only if the current baselines ________.

A.

Are off by 10%

B.

Are off by 20%

C.

Make no sense

D.

Are bad

Категории