MicrosoftВ® Office Project 2007 Step by Step (Step By Step (Microsoft))

For Microsoft Office Project 2007 to calculate earned value amounts for a project plan, you must first do the following:

Earned value analysis uses the following three key values to generate all schedule indicator and cost indicator values:

The earned value analysis schedule and the cost variance are directly related, but it’s simpler to examine each independently. To accommodate this, Project groups the earned value schedule and cost indicator fields into different tables, along with a third table that combines the key fields of both schedule and cost indicators:

In this exercise, you set the status date and view earned value schedule indicators for the project plan.

Be Sure To start Microsoft Office Project 2007 if it’s not already running.

Important 

If you are running Project Professional, you may need to make a one-time adjustment to use the Computer account and to work offline. This ensures that the practice files you work with in this chapter do not affect your Project Server data. For more information, see “Starting Project Professional” on page 11.

Open Short Film Project 18a from the Documents\Microsoft Press\Project 2007 SBS \Chapter 18 Earned Value folder. You can also access the practice files for this book by clicking Start, All Programs, Microsoft Press, Project 2007 Step by Step, and then selecting the chapter folder of the file you want to open.

1. On the File menu, click Save As.

The Save As dialog box appears.

2. In the File name box, type Short Film Project 18, and then click Save.

3. On the View menu, point to Table: Entry, and click More Tables.

The More Tables dialog box appears. In it, you see the three earned value tables.

4. On the Tables list, select Earned Value Schedule Indicators, and click the Apply button.

Project displays the Earned Value Schedule Indicators table in the Task Sheet view. Next, you will set the project status date. Unless you specify a status date, Project uses the current date when performing earned value calculations.

5. On the Project menu, click Project Information.

The Project Information dialog box appears.

6. In the Status Date box, type or select 6/20/2008, and click OK.

June 20 is the date that includes recent work completed on this project.

Here you can see the earned value schedule indicators for the project plan, summary tasks, and subtasks.

Tip 

If any column displays pound signs (###) or the values are not fully visible, double-click the column heading’s right edge to widen it.

All earned value numbers are reported either as dollars or as index ratios for easy comparison; negative cost values appear in parentheses. Note the information in the following columns:

Tip 

Here’s a quick way to get help about an earned value field or any field in a table in Project. Point to the column heading, and in the ScreenTip that appears, click the Help On <Field Name> link. Information about that field appears in the Help window.

You can use these schedule indicator values to address the question, “At the rate you’re making progress, is there enough time left to complete the project?” In the case of the short film project, one area to investigate is the low SPI for the production work completed thus far and whether the cause of that problem is likely to affect the remaining production work.

The values in the Earned Value Schedule Indicators table inform us about schedule performance, but they do not directly inform us about cost performance. You examine cost performance in the next section.

Категории