MicrosoftВ® Office Project 2007 Step by Step (Step By Step (Microsoft))

BAC. See Budget at completion (BAC)

Bar Styles dialog box, 316, 353, 355

Base calendar, 418

Baseline

defined, 122, 286–287

saving, 122–125

saving multiple, 124

updating, 286–290

when to save, 123

Baseline cost, 209–210, 318

BCWP. See Budgeted cost of work performed (BCWP)

BCWS. See Budgeted cost of work schedule (BCWS)

Bottom-up planning, 46

Budget. See Cost

Budget at completion (BAC), 395

Budget Cost Report, 321

Budgeted cost of work performed (BCWP), 391, 393, 395, 397

Budgeted cost of work schedule (BCWS), 391, 393, 395

Budgeted cost of work scheduled (BCWS), 397

Build Team from Enterprise, 443–444

Категории