The Calendar view is probably the simplest view available in Project; however, even the Calendar view offers several formatting options. This view is especially useful for sharing schedule information with resources or other stakeholders who prefer a traditional “month-at-a-glance” format rather than a more detailed view, such as the Gantt Chart view.
In this exercise, you reformat summary and critical tasks in the Calendar view.
-
On the View menu, click Calendar.
The Calendar view appears. It displays four weeks at a time, and it draws task bars on the days on which tasks are scheduled. Depending on your screen resolution, you might see additional task bars in the Calendar view.
-
On the Format menu, click Bar Styles.
The Bar Styles dialog box appears. The additional item type you would like to show on the Calendar view is a summary bar.
-
In the Task type box, click Summary.
-
In the Bar type box, click Line in the drop-down list.
The next item type to reformat is critical tasks.
-
In the Task type box, click Critical.
-
In the Pattern box, select the second option in the drop-down list: the solid black bar.
-
In the Color box, select Red from the drop-down list.
Your screen should look similar to the following illustration:
-
Click OK to close the Bar Styles dialog box.
-
On the Format menu, click Layout Now.
Project applies the format options to the Calendar view. Rather than scrolling through the Calendar view, you can jump right to a specific date.
-
On the Edit menu, click Go To.
-
In the Date box (not the ID box), type or select 9/26/05, and then click OK.
The Calendar view displays the first critical tasks. Your screen should look similar to the following illustration: