Six Sigma Tool Navigator: The Master Guide for Teams
| AKA | N/A |
| Classification | Changing/Implementing (CI) |
Tool description
A monthly assessment schedule displays all sequential activities of a project, program, or some scheduled event. It reflects the milestone start and completion dates, the length of scheduled activities, and early completion or slipped dates. It serves as a valuable attachment for any status report.
Typical application
-
To assess monthly the status of scheduled activities for the purpose of overall project management.
-
To plan and schedule a project, program or major event.
-
To monitor the progress of a project.
Problem-solving phase
| Select and define problem or opportunity | |
| → | Identify and analyze causes or potential change |
| → | Develop and plan possible solutions or change |
| → | Implement and evaluate solution or change |
| → | Measure and report solution or change results |
| Recognize and reward team efforts |
Typically used by
| Research/statistics | |
| Creativity/innovation | |
| 1 | Engineering |
| 2 | Project management |
| 3 | Manufacturing |
| Marketing/sales | |
| 7 | Administration/documentation |
| 4 | Servicing/support |
| 5 | Customer/quality metrics |
| 6 | Change management |
before
-
Gap Analysis
-
Force Field Analysis (FFA)
-
Barriers-and-Aids Analysis
-
Activity analysis
-
Checklist
after
-
Action Plan
-
Consensus Decision Making
-
Measurement Matrix
-
Countermeasure Matrix
-
Presentation
Notes and key points
Schedule milestone dates description:
Step-by-step procedure
-
STEP 1 A team assembles for the purpose of identifying and placing into sequential order all of the activities to complete a project, program, or major event. See example Annual Corporate-wide TQM Symposium Plan.
-
STEP 2 A monthly assessment schedule form is used to list all activities.
-
STEP 3 Next, the team reaches consensus on the length of the listed activities and the start and completion dates of each activity.
-
STEP 4 The draft of the schedule is completed by inserting all milestone dates and connecting lines under the schedule covering a specific time period, as shown in this example.
-
STEP 5 The team verifies all information, dates the chart, and attaches the chart to an action plan.
Example of tool application