| 1. | Who has overall responsibility for quality planning?
| A. | Project manager |
| B. | Quality manager |
| C. | Senior management |
| D. | Project planner |
|
| 2. | Which input is not used for risk identification?
| A. | Project charter |
| B. | Scope statement |
| C. | Project management plan |
| D. | Academic studies |
|
| 3. | Which risk response is most likely to involve contingency reserves?
| A. | Transfer |
| B. | Mitigate |
| C. | Acceptance |
| D. | Share | |
| 4. | Which contract type would be best for the seller if the scope of work is not well defined?
| A. | Fixed price |
| B. | Purchase order |
| C. | Time and material |
| D. | Cost plus incentive fee | |
| 5. | Which of the following activities is not part of risk management planning?
| A. | Developing a risk management plan |
| B. | Identifying risk categories |
| C. | Updating risk register |
| D. | Determining risk roles and responsibilities | |
| 6. | Which of the following is not a responsibility of the project manager?
| A. | Acquiring HR resources for the project team |
| B. | Managing overall responsibility for quality in the organization |
| C. | Overall responsibility for risk on the project |
| D. | Overall responsibility for customer satisfaction on the project |
|
| 7. | Which project document is best suited for tracking costs of resources?
| A. | Resource breakdown structure |
| B. | Organizational breakdown structure |
| C. | Work breakdown structure |
| D. | Risk breakdown structure |
|
| 8. | Which document is best suited for tracking the assignment of all resources to specific tasks?
| A. | Staffing management plan |
| B. | Organizational breakdown structure |
| C. | Position description |
| D. | RACI matrix |
|
| 9. | Which subsidiary plan/component documents the quality objectives for the project?
| A. | Quality management plan |
| B. | Quality baseline |
| C. | Process improvement plan |
| D. | Quality control checklist | |
| 10. | Which quality theory outlines 14 points and calls for quality awareness at all levels of the organization?
| A. | CMM |
| B. | Kaizen |
| C. | TQM |
| D. | Malcolm-Baldrige |
|