Production readiness—IV: Home plant facility validation and start of planned ramp-up. Build of saleable products for fast feedback.
Deliverables/Requirements—1st review
-
Production preparation
-
Assembly plant process validated
-
-
Build and test
-
Product build and assessed
-
Begin product and system process validation (PV) testing
-
Homologation compliance testing complete
-
Deliverables/Requirements—2nd review
-
Brand vision/marketing plans
-
Service scan-tool code and manuals released
-
Final pacing established
-
-
Program planning and resource management
-
Resource requirement assessment complete
-
-
Production preparation
-
Control plans for production implemented
-
Diagnostics and service procedures published
-
Workstation and launch readiness complete
-
Home-line installation and validation complete
-
-
Sourcing and logistics
-
Material handling validated
-
Certified components and systems received for build
-
-
Build and test
-
Product and system PV testing complete
-
Issues identified/resolved and corrective actions verified
-
-
Program and process assessment
-
Program assessment (function, product cost, program cost, timing and process conformance)
-
Lessons learned, documented and shared
-
|