9.12 Overruns

This is something you need to be monitoring in real time. Know your budget and track against it, or be in constant touch with the people in accounting or procurement who perform that service. On a large project, there will be plenty of give and take. For instance, we budgeted millions for a rollout component that cost 15 percent less a year later when we actually made the buy. In that same project, we abandoned a new technology after it was deemed unstable, but significant monies were spent before we pulled the plug. So, our savings in the first instance were essentially negated by the loss in the latter.