The Sprint retrospective meeting is time-boxed to 3 hours.
-
It is attended only by the Team, the ScrumMaster, and the Product Owner. The Product Owner is optional.
-
Start the meeting by having all Team members answer two questions:
-
What went well during the last Sprint?
-
What could be improved in the next Sprint?
-
-
The ScrumMaster writes down the Team ‚ s answers in summary form.
-
The Team prioritizes in which order it wants to talk about the potential improvements.
-
The ScrumMaster is not at this meeting to provide answers, but to facilitate the Team ‚ s search for better ways for the Scrum process to work for it.
-
Actionable items that can be added to the next Sprint should be devised as high-priority nonfunctional Product Backlog. Retrospectives that don ‚ t result in change are sterile and frustrating.