You should now be able to produce a final work breakdown structure. The steps taken to reach this stage are:
-
Turn the macro plan through 90 degrees, creating a number of potential work packages.
-
Interpret and question the results in order to decide the work packages.
-
Complete a template for each work package, giving a broad outline and targets for the schedule production.
-
Produce an initial schedule using brainstorming techniques.
-
Translate the work package and its associated schedule into a set of deliverables.
-
From the deliverables, work with experts to produce a schedule.
-
Revise all work packages to check all information is coherent .
-
Get steering group approval for the plan.
Following the steps outlined should ensure that your project is properly planned and has a completed business case and a completed work breakdown structure. In addition, the people in the project should have a clear understanding of what they personally have to do.