PMP Project Management Professional Study Guide, Third Edition (Certification Press)

 < Day Day Up > 


As promised, this section covers all of the information you must know going into the exam. It's highly recommended that you create a method to recall this information. Here goes.

The 39 Project Management Processes

Table A-1 shows the 39 project management processes. The intersection of the Knowledge Area and each stage (Initiating, Planning, Executing, Controlling, and Closing) describes the activity that happens at that point in the project. For example, follow the Project Scope Management row and the Controlling column to find Scope verification and change control. -

Table A-1: The 39 Project Management Processes

Knowledge Area

Initiating

Planning

Executing

Controlling

Closing

Project Integration Management

 

Developing the project plan.

Project Plan Execution

Integrated Change Control

 

Project Scope Management

Project Initiation

Creating and defining the project scope.

 

Scope verification and change control

 

Project Time Management

 

Defining activities, their sequence and their estimated duration. Developing the project schedule.

 

Schedule control

 

Project Cost Management

 

Determining the required resources, their estimated costs, and completing cost budgeting.

 

Enforcing cost control.

 

Project Quality Management

 

Planning for quality.

Adhering to the performing organization's quality assurance requirements.

Enforcing quality control on the project.

 

Project Human Resources Management

 

Completing organizational planning and staff acquisition

Ensuring team development.

  

Project Communications Management

 

Creating the Communications Management Plan.

Distributing the required information to the appropriate parties.

Reporting on project performance.

Completing administrative closure.

Project Risk Management

 

Completing risk management planning, risk identification, qualitative and quantitative risk analysis, and risk responses.

 

Monitoring and controlling risk.

 

Project Procurement Management

 

Completing the procurement and solicitation planning.

Soliciting vendors to participate on the project. Completing source selection based on defined criterion, and then following-through with contract administration.

 

Completing the contract closeout.

Magic PMP Formulas

The following shows the major formulas you should know for the exam:

Earned Value Management Formulas

The following shows the EVM formulas you should know for the exam:

Quick PMP Facts

This section has some quick facts you should be know at a glance. Hold on, this moves pretty fast.

Organizational Structures

Organizational structures are relevant to the project manager's authority. A project manager has authority from weakest to highest in the following order:

WBS Facts

The Work Breakdown Structure is the big picture of the project deliverables: it is not the activities that will create the project, but the components the project will create. The WBS helps the project team and the project manager create accurate cost and time estimates. The WBS also helps the project team and the project manager create an accurate activity list. The WBS is an input to five planning processes:

Project Scope Facts

Projects are temporary endeavors to create a unique product. Projects are selected by one of two methods:

The project scope defines all of the required work, and only the required work, to complete the project. Scope management is the process of ensuring that the project work is within scope and protecting the project from scope creep. The scope statement is the baseline for all future project decisions, as it justifies the business need of the project. There are two types of scope:

Scope verification is the process completed at the end of each phase and of each project to confirm that the project has met the requirements. It leads to formal acceptance of the project deliverable.

Project Time Facts

Time can be a project constraint. Effective time management is the scheduling and sequencing of activities in the best order to ensure that the project completes successfully and in a reasonable amount of time. These are some key terms for time management:

There are three types of dependencies between activities:

Project Cost Facts

There are several methods of providing project estimates:

There are four types of costs attributed to a project:

Quality Management Facts

The cost of quality is the money spent investing in training; in meeting requirements for safety and other laws and regulations; and in taking steps to ensure quality acceptance. The cost of nonconformance is the cost associated with rework, downtime, lost sales, and waste of materials.

Some common quality management charts and methods include the following:

Human Resource Facts

There are several human resource theories the PMP candidate should be familiar with on the PMP Exam. They are the following:

Communication Facts

Communicating is the most important skill for the project manager. With that in mind, here are some key facts on communications:

Risk Management Facts

Risks are unplanned events that can have positive or negative effects on the projects. Most risks are seen as threats to the project success-but not all risks are bad. For example, there is a 20 percent probability that the project will realize a discount in shipping, which will save the project $15,000. If this risk happens the project will save money, if the risk doesn't happen the project will have to spend the $15,000. Risks should be identified as early as possible in the planning process. A person's willingness to accept risk is the Utility Function (also called the Utility Theory). The Delphi Technique can be used to build consensus on project risks.

The only output of the risk planning is the Risk Management Plan. There are two broad types of risks:

Risks can be responded to in one of four methods:

Procurement Facts

A Statement of Work (SOW) is provided to the potential sellers so they can create accurate bids, quotes, and proposals for the buyer. A bidders' conference may be held so sellers can query the buyer on the product or service to be procured.

A contract is a formal agreement, preferably written, between a buyer and seller. On the PMP exam, procurement questions are usually from the buyer's point of view. All requirements the seller is to complete should be clearly written in the contract. Requirements of both parties must be met, or legal proceedings may follow. Contract types include the following:


 < Day Day Up > 

Категории