PMP Project Management Professional Study Guide, Third Edition (Certification Press)

 < Day Day Up > 


Now that the activity list has been created, the activities must be arranged in a logical sequence. This process calls on the project manager and the project team to identify the logical relationships between activities-and the preferred relationship between activities. This can be accomplished a few different ways:

On the Job 

'Sticky notes' can help sequence events. Put your activities on sticky notes and then plot them out on a white board. Draw arrows to show the relationship between activities. Want to make a change? It's easy to rearrange the notes and the relationships.

Considering the Inputs to Activity Sequencing

Figure 6-3 shows the complete process of activity sequencing. There are many approaches to completing the activity sequencing. Perhaps the greatest approach, however, is that activity sequencing is done with the project team, not as a solo activity.

click to expand Figure 6-3: Activity sequencing relies on inputs to create the final sequence of events.

The project manager must rely on the project team and the inputs to activity sequencing:

Creating Network Diagrams

Network diagrams visualize the project work. A network diagram shows the relationship of the work activities and how the work will progress from start to completion. Network diagrams can be extremely complex or easy to create and configure. Most network diagrams in today's project management environment use an approach called 'activity-on-node' to illustrate the activities and the relationship between activities. Older network diagramming methods used 'activity-on-arrows' to represent the activities and their relationships.

Using the Precedence Diagramming Method

The Precedence Diagramming Method (PDM) is the most common method of arranging the project work visually. The PDM puts the activities in boxes, called nodes, and connects the boxes with arrows. The arrows represent the relationship and the dependencies of the work packages. The following illustration shows a simple network diagram using PDM.

Exam Watch

PDM is also known as AON- activity-on-node. It's the most common approach to network diagramming since it's used by most project management information systems but can also be done manually.

Relationships between activities in a PDM constitute one of four different types (as shown in Figure 6-4):

Figure 6-4: PDM relationships can vary, but most use the finish-to-start approach.

Using the Arrow Diagramming Method

The Arrow Diagramming Method (ADM) approach to activity sequencing uses arrows to represent the activities. The arrows are 'connected' on nodes. ADM only uses finish-to-start relationships. In some instances, dummy activities are required to express the logical relationship between two activities. A dummy activity is illustrated with a dashed arrow between the nodes. The following illustration is a simple example of an ADM network diagram.

Exam Watch

Only professional scheduling engineers should use the SS, FF, and SF relationships. Don't worry about the SF for your exam studying time; you likely won't encounter it.

ADM is an example of activity-on-arrow (AOA) networks. This approach is not as popular as PDM, but may still be prevalent in some industries. ADM can be created manually or through a PMIS.

Using Conditional Diagramming Methods

Conditional diagramming methods are more complex and structured than ADM or PDM. Conditional diagramming methods include system dynamics and the graphical evaluation and review technique (GERT). These models allow for loops and conditional branching. For example, GERT may require that tests of the product be performed several times before the project may continue. Based on the outcome of the testing, the project may use one of several paths to enable its completion. In addition, GERT allows for probabilistic clarification of work package estimates.

Utilizing Network Templates

Just as a project manager can rely on WBS templates, there may be network templates available to streamline the planning process or to conform to a predetermined standard. Network templates can represent an entire project if appropriate, though portions of a network template, such as the required project management activities, are common.

Exam Watch

Note that GERT allows for conditional advancement. ADM and PDM offer no loops or branching.

The portions of a network template are also known as subnets or fragnets. Subnets are often associated with repetitive actions within a network diagram. For example, each floor in a high-rise apartment building may undergo the same or similar actions during construction. Rather than complete the network diagram for each floor, a subnet can be implemented.


 < Day Day Up > 

Категории