PMP Project Management Professional Study Guide, Third Edition (Certification Press)

 < Day Day Up > 


After all the challenges of examining, sequencing, and calculating the project activities, a working schedule is created. Schedule development, like most of project management's planning processes, moves through progressive elaboration. As the project moves forward, discoveries, risk events, or other conditions may require the project schedule to be adjusted. In this section, we'll discuss the project schedule and how it is managed.

Examining the Project Schedule

The project schedule includes, at a minimum, a date for when the project begins and a date when the project is expected to end. The project schedule is considered proposed until the resources needed to complete the project work are ascertained. In addition to the schedule, the project manager should include all of the supporting details. Project schedules can be presented in many different formats, such as:

Utilizing the Schedule Management Plan

The schedule management plan is a subsidiary plan of the overall project plan. It is used to control changes to the schedule. A formal schedule management plan has procedures that control how changes to the project plan can be proposed, accounted for, and then implemented. An informal schedule management plan may consider changes on an instance-by-instance basis.

Updating the Resource Requirements

Due to resource leveling, additional resources may need to be added to the project. For example, a proposed leveling may extend the project beyond an acceptable completion date. To reach the project end date the project manager elects to add additional resources to the critical path activities. The resources the project manager adds should be documented, the associated costs accounted for, and approved.


 < Day Day Up > 

Категории