IT Project Management: On Track from Start to Finish, Third Edition
Exercise 1
The solution to Exercise 1 can be found in the file Completed Exercise One, which appears on the CD-ROM in the CH8 folder.
Exercise 2
The solution to Exercise 2 can be found in the file Completed Exercise Two, which appears on the CD-ROM in the CH8 folder.
Exercise 3
The solution to Exercise 3a can be found in the file Completed Exercise Three, which appears on the CD-ROM in the CH8 folder.
The solution to Exercise 3b is as follows :
| Term | Value |
|---|---|
| Budget at Completion | $550,000.00 |
| Percent Complete | 40% |
| Planned Value | $220,000.00 |
| Actual Costs | $225,000.00 |
| Earned Value | $220,000.00 |
| Cost Variance | $ (5,000.00) |
| Schedule Variance | $ - |
| Cost Performance Index | 0.98 |
| Schedule Performance Index | 1.00 |
| Estimate at Completion | $562,500.00 |
| Estimate to Complete | $337,500.00 |
| To Complete Performance Index | 0.98 |