The Process of Building a WBS

Now that we understand what a WBS is and the importance it plays to our project, let's review the key techniques, guidelines, and principles in building an effective WBS.

In general, the process of breaking down work is something we do frequently and is a straightforward logical endeavor. However, there are frequently two common challenges in the WBS development process.

Major deliverables should come from the project definition document and are likely second-level WBS elements.

There is no one way to organize a WBS. It should be organized in a manner that emphasizes the most important aspects and that best communicates the entire scope of the project to your stakeholders.

 

Getting Started

To start the work decomposition process, think about the following:

To continue the work decomposition process, think about these questions:

Guidelines for Effective WBS

Here are a few "guidelines" regarding the development of the project WBS that you will want to keep in mind:

The level of depth (granularity) for the work package level in a WBS (lowest levels) will vary. It depends on what level of detail the project manager needs for effective management and control of the project.

In a program, or on large projects, the work package level may represent efforts in the hundreds of hours. In these cases, it is expected that the teams assigned to these work packages (or subprojects) will define the detail activities and tasks needed to complete the work package. From a practical standpoint, these teams should develop their own WBS that can then be rolled-up into the master WBS.

caution

Most troubled projects have WBS elements that are too large. If each lower level element should be completed within the standard reporting period (every week or every two weeks), it is much easier to track actual progress and to take any corrective actions.

 

Knowing When to Stop

The other aspect of WBS development that creates frequent uncertainty is knowing when to stop. To determine if you have enough detail in your WBS, review these questions for each lower level item:

The importance of the WBS cannot be over-emphasized. Since the correctness and completeness of the WBS has a direct impact on how well we determine our resource needs, estimate the work efforts, and properly sequence the work, it is the foundation that drives our schedule and most of our planning efforts.

The Absolute Minimum

At this point, you should have a solid understanding of the following:

  • A WBS is a logical breakdown of all the work to be performed by the project.
  • A WBS is neither the project schedule nor the project plan.
  • The WBS should be developed with the project team.
  • The WBS is a vital tool to the project manager.
  • Avoid judging a current work process or the people involved before you understand why it is done this way or how it evolved to the current point.
  • How to evaluate a WBS.
  • How to avoid the common challenges and issues with WBS development.
  • The WBS is the foundation for developing a realistic schedule, determining project resource needs, and figuring an accurate project budget.
  • The work packages included in the WBS should be detailed enough to support effective management and control.
  • The maximum size of a WBS work package should correspond to the standard reporting period for the project.

The map in Figure 6.4 summarizes the main points we reviewed in this chapter.

Figure 6.4. Developing a work breakdown structure overview.

Категории